Order in Council
At Wellington this 24th day of June 2013
Present:
His Excellency the Governor-General in Council
Note
The Parliamentary Counsel Office has made editorial and format changes to this version using the powers under subpart 2 of Part 3 of the Legislation Act 2019.
Note 4 at the end of this version provides a list of the amendments included in it.
These regulations are administered by the Ministry for the Environment.
Pursuant to sections 27(1), 30(1), and 35 of the Exclusive Economic Zone and Continental Shelf (Environmental Effects) Act 2012, His Excellency the Governor-General makes the following regulations, acting on the advice and with the consent of the Executive Council and on the recommendation of the Minister for the Environment given after the requirements of sections 32, 33, and 34 of that Act have been met.
Contents
Regulations
1 Title
These regulations are the Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Regulations 2013.
2 Commencement
These regulations come into force on 28 June 2013.
3 Interpretation
In these regulations, unless the context otherwise requires,—
authorised launch deposit area means the area to the north, east, north-west, south, and south-west of New Zealand that—
(a)
is bounded by the line extending from 46º05′S 166º11′E to 46º52′S 161º48′E (south-west of the South Island); and
(b)
is bounded by the line extending from 34º13′S 172º40′E to 30º55′S 171º10′E (north-west of the North Island); but
(c)
does not extend beyond the exclusive economic zone and continental shelf
closed seamount area means the areas described in—
(a)
regulation 2B(2)(a) and (b) of the Fisheries (Auckland and Kermadec Areas Commercial Fishing) Regulations 1986; and
(b)
regulation 6B(2)(a) and (b) of the Fisheries (Central Area Commercial Fishing) Regulations 1986; and
(c)
regulation 4C(2)(a) to (e) of the Fisheries (South-East Area Commercial Fishing) Regulations 1986; and
(d)
regulation 15JA(2)(a) to (c) and (e) of the Fisheries (Southland and Sub-Antarctic Areas Commercial Fishing) Regulations 1986
customary marine title group has the meaning given in section 9(1) of the Marine and Coastal Area (Takutai Moana) Act 2011
EPA means the Environmental Protection Authority
exploration—
(a)
means any activity (including research) undertaken for the purpose of—
(i)
identifying mineral deposits or occurrences:
(ii)
evaluating the feasibility of mining particular deposits or occurrences of 1 or more minerals; and
(b)
includes any drilling except drilling for petroleum, any dredging, or any excavation (whether surface or subsurface) that is reasonably necessary to determine the nature or size of a mineral deposit or occurrence; but
(c)
excludes seismic surveying
marine scientific research—
(a)
means research (whether fundamental or applied) carried out for the purpose of increasing knowledge about the marine environment, marine resources, or living marine organisms; and
(b)
includes any related scientific activity; but
(c)
excludes—
(i)
any research carried out in relation to prospecting, exploration, or mining; and
(ii)
seismic surveying
mining has the meaning given in section 2(1) of the Crown Minerals Act 1991
permitted marine structure means a structure constructed or placed on the seabed during, or for the purpose of carrying out, a permitted activity
prospecting—
(a)
means any activity (including research) undertaken for the purpose of identifying seabed or subsoil likely to contain mineral deposits or occurrences; and
(b)
includes the following activities:
(i)
geological, geochemical, and geophysical surveying; and
(ii)
taking samples by hand or handheld methods; and
(iii)
taking small samples offshore by low-impact mechanical methods; but
(c)
excludes seismic surveying
seismic survey means a survey of the geology of the seabed, or the structures beneath the seabed, carried out by projecting pressure waves into the layers beneath the seabed and detecting and measuring the reflected signals; and seismic surveying has a corresponding meaning
sensitive environment, in relation to the exclusive economic zone or continental shelf, means an area that contains any of the habitats listed in the first column of Schedule 6 (as described in the second column of that schedule)
space vehicle means a vehicle that—
(a)
travels or is intended to travel above controlled airspace (meaning controlled airspace designated by rules made under section 52 of the Civil Aviation Act 2023); and
(b)
jettisons nothing other than the following material during its normal operation:
(i)
aluminium, brass, copper, Inconel, nickel, steel, and zinc; and
(ii)
adhesive, cork, foam, paint, glass fibre composite, carbon fibre composite, plastic, lithium batteries, and printed circuit boards
submarine cable means a submarine cable within the meaning of section 2 of the Submarine Cables and Pipelines Protection Act 1996.
Regulation 3 authorised launch deposit area: replaced, on 5 April 2018, by regulation 4(1) of the Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Amendment Regulations 2018 (LI 2018/53).
Regulation 3 authorised test launch deposit area: revoked, on 5 April 2018, by regulation 4(2) of the Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Amendment Regulations 2018 (LI 2018/53).
Regulation 3 closed seamount area: inserted, on 5 April 2018, by regulation 4(3) of the Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Amendment Regulations 2018 (LI 2018/53).
Regulation 3 space vehicle: inserted, on 21 October 2016, by regulation 5 of the Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Amendment Regulations 2016 (LI 2016/235).
Regulation 3 space vehicle paragraph (a): amended, on 5 April 2025, by section 486 of the Civil Aviation Act 2023 (2023 No 10).
4 Purpose
These regulations—
(a)
prescribe certain activities that are permitted activities for the purposes of section 20 of the Act; and
(b)
prescribe conditions for undertaking certain permitted activities; and
(c)
require the EPA to monitor compliance with those conditions.
Permitted activities
5 Marine scientific research, prospecting, and exploration
(1)
Marine scientific research, prospecting, and exploration are permitted activities if the person undertaking the activity concerned complies with the conditions in subclause (2).
(2)
The conditions are that the person—
(a)
complies with the pre-activity requirements in Schedule 1; and
(b)
at least 5 working days before commencing the activity,—
(i)
carries out an initial environmental assessment; and
(ii)
provides the EPA with an initial environmental assessment and sensitive environments contingency plan for the area that complies with the requirements in Schedule 2; and
(c)
notifies the EPA, within 24 hours, of the date on which the person commences the marine scientific research, prospecting, or exploration (as the case may be); and
(d)
complies with the logbook requirements in Schedule 3; and
(e)
ensures that all reasonable measures are taken to avoid, mitigate, or remedy adverse effects of the activity on any sensitive environment encountered; and
(f)
ensures that no more material is removed from the seabed or subsoil than is reasonably necessary to undertake the activity; and
(g)
ensures that no person sells any non-living natural material that was removed from the seabed or subsoil during, or for the purpose of, undertaking the activity; and
(h)
notifies the EPA, within 24 hours, of the date on which the person completes the marine scientific research, prospecting, or exploration (as the case may be); and
(i)
complies with the post-activity requirements in Schedule 4.
(3)
To avoid doubt, this regulation does not apply to activities described in section 20(5) of the Act.
Examples of kinds of measures that could be taken to avoid, mitigate, or remedy adverse effects of an activity
The kinds of measures include—
-
(a)
carrying out the activity in another place:
-
(b)
reducing contact with the seabed:
-
(c)
carrying out alternative lower-impact activities:
-
(d)
changing the method(s) of operation to lower the impact of the activity on the environment.
6 Permitted marine structures
(1)
The maintenance or repair of a permitted marine structure is a permitted activity.
(2)
The alteration, extension, or removal of a permitted marine structure is a permitted activity if the person undertaking the activity concerned complies with the conditions in subclause (3).
(3)
The conditions referred to in subclause (2) are that the person—
(a)
complies with the pre-activity requirements in Schedule 1; and
(b)
complies with the post-activity requirements in Schedule 4.
7 Seismic surveys
(1)
Seismic surveying is a permitted activity if the person undertaking the seismic survey complies with the Department of Conservation’s 2013 Code of Conduct for Minimising Acoustic Disturbance to Marine Mammals from Seismic Survey Operations.
(2)
Subclause (1) does not apply to seismic surveying within Te Rohe o Te Whānau Puha Whale Sanctuary established under section 11 of the Kaikōura (Te Tai o Marokura) Marine Management Act 2014.
Regulation 7(1): amended, on 29 November 2013, by regulation 4 of the Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Amendment Regulations 2013 (SR 2013/467).
Regulation 7(2): inserted, on 8 August 2014, by section 30 of the Kaikōura (Te Tai o Marokura) Marine Management Act 2014 (2014 No 59).
8 Submarine cables
(1)
The placement of a submarine cable on or under the seabed, or the removal of a submarine cable from the seabed, is a permitted activity if the person undertaking the activity concerned complies with the conditions in subclause (2).
(2)
The conditions are that the person—
(a)
complies with the pre-activity requirements in Schedule 1; and
(b)
notifies the EPA, within 24 hours, of the date on which the person commences the activity concerned; and
(c)
notifies the EPA, within 24 hours, of the date on which the person completes the activity concerned; and
(d)
complies with the post-activity requirements in Schedule 4.
(3)
The maintenance, repair, alteration, or extension of an existing submarine cable is a permitted activity.
(4)
In subclause (3), existing submarine cable means a submarine cable that was placed on or under the seabed—
(a)
in accordance with subclause (1); or
(b)
before the date on which these regulations came into force.
8A Deposit of material on seabed from launch of space vehicle
The deposit on the seabed of material jettisoned from any launch of a space vehicle from New Zealand is a permitted activity if the person undertaking the activity complies with the following conditions:
(a)
there are no more than 100 space vehicle launches from New Zealand in total (regardless of who undertook the activity); and
(b)
the material jettisoned from the space vehicle is—
(i)
deposited within the authorised launch deposit area; but
(ii)
not deposited within the closed seamount area; and
(c)
the person complies with the pre-activity and post-activity requirements in Schedule 4A.
Regulation 8A: replaced, on 5 April 2018, by regulation 5 of the Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Amendment Regulations 2018 (LI 2018/53).
Miscellaneous provisions
9 EPA to monitor permitted activities
The EPA must monitor permitted activities to determine whether the activities are being undertaken in accordance with conditions imposed by these regulations.
10 EPA to notify relevant iwi, hapū, customary marine title group, and protected customary rights group of permitted activity
(1)
As soon as practicable after the EPA has been notified under regulation 5(2)(c) or 8(2)(b) that a person has commenced a permitted activity, the EPA must notify every iwi, hapū, customary marine title group, and protected customary rights group that it identified under Schedule 1, clause 1(3) that the activity has commenced.
(2)
As soon as practicable after the EPA has been notified under regulation 5(2)(h) or 8(2)(c) that a person has completed a permitted activity, the EPA must notify every iwi, hapū, customary marine title group, and protected customary rights group that it identified under Schedule 1, clause 1(3) that the activity has been completed.
11 Forms
The forms set out in Schedule 5 are prescribed for the following purposes under the Act:
(a)
a pre-activity notice (form 1):
(b)
a report of pre-activity notification of relevant iwi (form 2):
(c)
an initial environmental assessment and sensitive environments contingency plan (form 3):
(d)
a post-activity report (form 4).
12 Transitional provision
The following provisions of Schedule 1 do not apply to an activity that commences on or before 26 August 2013:
(a)
Schedule 1 Pre-activity requirements
1 Pre-activity notification to EPA
(1)
A person who intends to undertake a permitted activity must provide the EPA with the following information:
(a)
a description of the activity; and
(b)
the date on which the activity is expected to begin; and
(c)
the activity’s expected duration; and
(d)
the co-ordinates of the area within which the activity will be conducted.
(2)
The information in subclause (1) must be provided—
(a)
no less than 40 working days before the activity commences; and
(b)
in form 1 set out in Schedule 5.
(3)
The EPA must provide the person who intends to undertake the permitted activity with a list of iwi, hapū, customary marine title groups, and protected customary rights groups whose existing interests the EPA considers may be affected by the activity.
(4)
The EPA must provide the information in subclause (3) within 10 working days after receiving a notice under subclause (1).
2 Pre-activity notification of relevant iwi
(1)
A person who intends to undertake a permitted activity must—
(a)
notify every iwi, hapū, customary marine title group, and protected customary rights group that the EPA has identified under clause 1(3) that he or she proposes to undertake the activity; and
(b)
provide those persons with a copy of the information provided to the EPA under clause 1(1) in form 1 set out in Schedule 5.
(2)
The notification in subclause (1) must be made at least 25 working days before the activity commences.
(3)
The person who intends to undertake the permitted activity must provide the EPA with—
(a)
a report detailing—
(i)
the persons notified under subclause (1); and
(ii)
how and when those persons were contacted; and
(iii)
the information that was provided to them; and
(iv)
the name and contact details of every respondent; and
(v)
a copy, or accurate summary, of every response received; and
(vi)
the outcome of any dialogue that was entered into between the person who intends to undertake the permitted activity and the respondents; and
(b)
details of any change that is proposed to the activity as a result of the notification process.
(4)
The information in subclause (3) must be provided—
(a)
no less than 5 working days before the activity commences; and
(b)
in form 2 set out in Schedule 5.
(5)
The information in subclause (3)(a)(v) must include a copy or accurate summary of any information provided by a respondent regarding—
(a)
the respondent’s environmental policies or environmental strategy plans; and
(b)
any culturally sensitive areas, including waahi tapu, that may be affected by the proposed permitted activity; and
(c)
the likely impacts of the proposed permitted activity; and
(d)
the respondent’s concerns about the proposed permitted activity.
Schedule 2 Contents of initial environmental assessment and sensitive environments contingency plan
1 Contents of plan
(1)
An initial environmental assessment and sensitive environments contingency plan must—
(a)
describe the activity concerned; and
(b)
state the co-ordinates of the area within which the activity will be conducted; and
(c)
describe in general terms (using the best available information) the environment likely to be encountered when the activity is being undertaken; and
(d)
identify and describe any sensitive environments that are likely to exist within the area; and
(e)
detail the methods that will be used to undertake the activity; and
(f)
in relation to any sensitive environment that is likely to be encountered,—
(i)
assess the feasibility of carrying out the activity in another location; and
(ii)
assess, in the following order, the feasibility of measures that could be taken to—
(A)
reduce the amount of contact with the seabed:
(B)
carry out alternative lower-impact activities:
(C)
change the methods of operation to lower the impact of the activity on the environment.
(2)
In this clause, best available information means the best information that, in the particular circumstances, is available without unreasonable cost, effort, or time.
2 Form of plan
The initial environmental assessment and sensitive environments contingency plan must be provided in form 3 set out in Schedule 5.
Schedule 3 Permitted activity logbook
1 Permitted activity logbook
A person who undertakes marine scientific research, prospecting, or exploration must—
(a)
keep a permitted activity logbook in an electronic form approved by the EPA; and
(b)
ensure that a copy of the information recorded in the logbook is provided to the EPA every week for the duration of the activity.
2 Logbook entries
(1)
The person must ensure that the following entries are made in the logbook:
(a)
the particulars stated in items 1, 2, and 3 of the table below, on the first page or pages; and
(b)
the particulars stated in item 4 of the table below, every time a sensitive environment is encountered; and
(c)
the particulars stated in item 5 of the table below, for every day on which no sensitive environment is encountered.
(2)
Every entry must—
(a)
state the date on which it is made and, if different, the date of the occurrence to which it relates; and
(b)
be entered into the logbook as soon as practicable after the occurrence to which it relates.
| Table—Logbook entries | |
| 1 | Details of person undertaking permitted activity, including—
|
| 2 | Detailed description of permitted activity, including—
|
| 3 | Location of permitted activity, including co-ordinates of area where activity will be undertaken. |
| 4 | Details of every sensitive environment encountered, including—
|
| 5 | Statement that no sensitive environment encountered, including—
|
Schedule 4 Post-activity requirements
1 Post-activity reports
(1)
A person who has undertaken a permitted activity must, within 60 working days after completing the activity, provide the EPA with a report containing—
(a)
a description of the activity undertaken; and
(b)
the dates on which the activity began and ended; and
(c)
the co-ordinates of the area(s) within which the activity was conducted; and
(d)
quantifiable estimates of the activity’s environmental footprint, including an estimate of the volume of any material removed from the seabed.
(2)
In the case of marine scientific research, prospecting, or exploration, the report must also include—
(a)
a description and the location of every sensitive environment that was encountered; and
(b)
details of the actions taken to avoid, mitigate, or remedy adverse effects of the activity on every sensitive environment encountered, and the reasons for choosing those particular actions.
2 Form of post-activity reports
The post-activity report must be provided in form 4 set out in Schedule 5.
Schedule 4A Pre-activity and post-activity requirements for deposit of material on seabed from launch of space vehicle
Schedule 4A: replaced, on 5 April 2018, by regulation 6 of the Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Amendment Regulations 2018 (LI 2018/53).
1 Pre-activity requirements
(1)
The person undertaking the activity must provide the EPA with the following information no later than 10 working days before the planned space vehicle launch:
(a)
the proposed dates and times of the launch; and
(b)
the predicted flight path or paths of the launch; and
(c)
the area in which the material jettisoned from the space vehicle is expected to land; and
(d)
details of any additional proposed actions to avoid, mitigate, or remedy any adverse effects of the activity on existing interests.
(2)
The EPA must publish on its Internet site the information provided under subclause (1) as soon as is reasonably practicable after the person provides it.
2 Post-activity requirements
(1)
The person undertaking the activity must—
(a)
provide the EPA with a post-activity report no later than 5 working days after the space vehicle launch; and
(b)
also provide the EPA with a post-activity report at quarterly intervals or after 10 consecutive launches (whichever happens first).
(2)
The post-activity report required by subclause (1)(a) must include the following information:
(a)
the date and time of the launch; and
(b)
the observed flight path of the launch; and
(c)
as far as is reasonably possible,—
(i)
the volume of material jettisoned from the space vehicle; and
(ii)
the co-ordinates of each area in which that material landed; and
(d)
details of any deviations from the pre-activity information provided under clause 1.
(3)
The post-activity report required by subclause (1)(b) must for each space vehicle launch—
(a)
advise if the person received any written complaint alleging that the conditions for undertaking the activity were breached; and
(b)
if a complaint was made, provide—
(i)
a summary of the complaint (which must include the date on which the complaint was received); and
(ii)
an explanation of how the person dealt with the complaint.
(4)
The EPA must publish a summary of any post-activity report provided under subclause (1)(a) or (b) on its Internet site as soon as is reasonably practicable after the person provides it.
Schedule 5 Forms
Form 1 Pre-activity notice
Regulation 11(a), Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Regulations 2013
To the Environmental Protection Authority, Private Bag 63002, Wellington 6140
Details of person undertaking permitted activity
Name:
Address:
Telephone number:
Email address:
Fax number:
Contact person:
General description of permitted activity
Type of activity:
Description of methods to be used to undertake the activity:
Timing of permitted activity
Proposed commencement date:
Approximate duration of activity (in days):
Timetable:
Location of permitted activity
Co-ordinates of area where activity will be undertaken:
Description of the current state of the area and the surrounding environment, including any known sensitive environments:
Description of the likely effects of the activity on the environment:
Other information
Name of ship or ships involved in activity:
International call sign or vessel number of the ship or ships involved:
Associated licence number (under the Continental Shelf Act 1964):
Associated permit number (under the Crown Minerals Act 1991):
Date:
Signature of authorised contact person:
Name:
Title:
Form 2 Report of pre-activity notification of relevant iwi
Regulation 11(b), Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Regulations 2013
To the Environmental Protection Authority, Private Bag 63002, Wellington 6140
Details of person undertaking permitted activity
Name:
Address:
Telephone number:
Email address:
Fax number:
Contact person:
General description of permitted activity
Type of activity:
Commencement date (proposed in the pre-activity notice):
Co-ordinates of area of the permitted activity (proposed in the pre-activity notice):
Other information
Persons notified:
How and when persons were notified:
Information provided:
Responses received:
[Attach copies, or accurate summaries, of submissions, including name and contact details of the respondents.]
Summary of dialogue with every iwi, hapū, customary marine title group, and protected customary rights group identified by the EPA:
[Attach copies, or accurate summaries, of the following information (if provided): the respondent’s environmental policies or environmental strategy plans, culturally sensitive areas or waahi tapu identified by the respondent, likely impacts identified by the respondent, and the respondent’s concerns about the permitted activity.]
Changes to pre-activity notice (if applicable)
Revised commencement date:
Revised duration of activity (in days):
Revised timetable:
Revised co-ordinates of the area where the activity will be undertaken:
Revised description of the current state of the area and the surrounding environment, including any known sensitive environments:
Revised description of the likely effects of the activity on the environment:
Revised description of methods to be used to undertake activity:
Other revised information:
Date:
Signature of authorised contact person:
Name:
Title:
Form 3 Initial environmental assessment and sensitive environments contingency plan
Regulation 11(c), Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Regulations 2013
To the Environmental Protection Authority, Private Bag 63002, Wellington 6140
Details of person undertaking permitted activity
Name:
Address:
Telephone number:
Email address:
Fax number:
Contact person:
General description of permitted activity
Type of activity:
Description of methods to be used to undertake the activity:
Location of permitted activity
Co-ordinates of area where activity will be undertaken:
Description of current state of the area and the surrounding environment, including any sensitive environments:
Description of likely effects of the activity on the environment:
Identification of sensitive environments
Description of any sensitive environments likely to exist in the area where the activity will be undertaken:
Contingency plan
Specify measures that could be taken to avoid, remedy, or mitigate the adverse effects of the activity on sensitive environments:
1
Can the activity be undertaken in another place? Yes/No*
Explain:
2
Can the activity be undertaken in a way that reduces the amount of contact with the seabed? Yes/No*
Explain:
3
Can different methods be used in undertaking the activity to lessen its effects on the sensitive environment? Yes/No*
Explain:
4
Can the activity be undertaken in a way that lessens its effects on the sensitive environment? Yes/No*
Explain:
| *Select one. |
Date:
Signature of authorised contact person:
Name:
Title:
Form 4 Post-activity report
Regulation 11(d), Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Regulations 2013
To the Environmental Protection Authority, Private Bag 63002, Wellington 6140
Details of person undertaking permitted activity
Name:
Address:
Telephone number:
Email address:
Fax number:
Contact person:
Description of permitted activity
Type of activity:
Period during which activity was undertaken:
Location of permitted activity
Co-ordinates of area where activity was undertaken:
Details of environment of area where activity undertaken
General description of the environment:
Description of any sensitive environment that was encountered in the area where the activity was undertaken:
Environmental footprint of activity
Estimation of the volume of material removed:
Estimation of the areas of seabed affected by each component of, or sample taken as part of, the activity (m2):
Details of measures taken to avoid, mitigate, or remedy adverse effects on the sensitive environment
Did you implement the contingency plan submitted to the EPA? Yes/No*
Explain:
| *Select one. |
Provide details of, and the reasons for, the measures taken to avoid, mitigate, or remedy the effects of the activity:
Date:
Signature of authorised contact person:
Name:
Title:
Schedule 6 Sensitive environments
| Sensitive environment | Indicator of existence of sensitive environment | |
|---|---|---|
| Stony coral thickets or reefs | A stony coral reef or thicket exists if—
|
|
| Xenophyophores (sessile protozoan) beds | A xenophyophore bed exists if average densities of all species of xenophyophore found (including fragments) equal or exceed 1 specimen per m2 sampled. |
|
| Bryozoan thickets | A bryozoan thicket exists if—
|
|
| Calcareous tube worm thickets | A sensitive tube worm thicket exists if—
|
|
| Chaetopteridae worm fields | A sensitive chaetopteridae worm field exists if worm tubes or epifaunal species—
|
|
| Sea pen field | A sea pen field exists if—
|
|
| Rhodolith (maerl) beds | A rhodolith bed—
|
|
| Sponge gardens | A sponge garden exists if metazoans of classes Demospongiae, Hexactinellida, Calcerea, or Homoscleromorpha—
|
|
| Beds of large bivalve molluscs | A bed of large bivalve molluscs exists if living and dead specimens—
|
|
| Macro-algae beds | A macro-algae bed exists if a specimen of a red, green, or brown macro-algae is found in a visual imaging survey or any sample. |
|
| Brachiopods | A brachiopod bed exists if 1 or more live brachiopods—
|
|
| Deep-sea hydrothermal vents |
A sensitive hydrothermal vent exists if a live specimen of a known vent species is found in a visual imaging survey or any sample. The following vent species are known to exist in New Zealand waters:
|
|
| Methane or cold seeps | A methane or cold seep exists if a single occurrence of one of the following taxa is found in a visual imaging survey or any sample:
|
Rebecca Kitteridge,
Clerk of the Executive Council.
Issued under the authority of the Legislation Act 2019.
Date of notification in Gazette: 27 June 2013.
Notes
1 General
This is a consolidation of the Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Regulations 2013 that incorporates the amendments made to the legislation so that it shows the law as at its stated date.
2 Legal status
A consolidation is taken to correctly state, as at its stated date, the law enacted or made by the legislation consolidated and by the amendments. This presumption applies unless the contrary is shown.
Section 78 of the Legislation Act 2019 provides that this consolidation, published as an electronic version, is an official version. A printed version of legislation that is produced directly from this official electronic version is also an official version.
3 Editorial and format changes
The Parliamentary Counsel Office makes editorial and format changes to consolidations using the powers under subpart 2 of Part 3 of the Legislation Act 2019. See also PCO editorial conventions for consolidations.
4 Amendments incorporated in this consolidation
Civil Aviation Act 2023 (2023 No 10): section 486
Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Amendment Regulations 2018 (LI 2018/53)
Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Amendment Regulations 2016 (LI 2016/235)
Kaikōura (Te Tai o Marokura) Marine Management Act 2014 (2014 No 59): section 30
Exclusive Economic Zone and Continental Shelf (Environmental Effects—Permitted Activities) Amendment Regulations 2013 (SR 2013/467)